Power Project
Bhusawal TPS Expansion (2 x 500 MW)
- Order for main plant equipment placed on M/s. BHEL on 23.01.07 (Zero date).
- Order for balance of plant placed on 05.11.07 on M/s Tata Projects Ltd.
- Supply of boiler materials commenced from 31.11.07.
- Boiler erection commenced on 26.03.08.
- Schedule for trial operation: Unit 1 - August, 2010, Unit 2 - December, 2010.
- Government of Maharashtra approved the above projects vide Government.
- Resolution no. vi ni k 2005 / pra. kra. 2044 / Oorja-4 dated 12.05.06.