Power Project

Bhusawal TPS Expansion (2 x 500 MW)

  • Order for main plant equipment placed on M/s. BHEL on 23.01.07 (Zero date).
  • Order for balance of plant placed on 05.11.07 on M/s Tata Projects Ltd.
  • Supply of boiler materials commenced from 31.11.07.
  • Boiler erection commenced on 26.03.08.
  • Schedule for trial operation: Unit 1 - August, 2010, Unit 2 - December, 2010.
  • Government of Maharashtra approved the above projects vide Government.
  • Resolution no. vi ni k 2005 / pra. kra. 2044 / Oorja-4 dated 12.05.06.